How to Use Spun Pole Design

On this page

Spun Concrete Pole Design

A spun concrete pole tapers towards the top, and the loads on it act at several heights: the conductors at the tip, cross-arms and equipment lower down. Its reinforcement is therefore not sized at one section. The calculation first finds the longitudinal steel and spiral required at every height of the pole. You then lay out the zones of constant reinforcement the shop will produce, and the calculation checks them. Why the design runs in these two stages is explained on the Spun Concrete Pole Design page. This page walks through the screens.

Creating the calculation

Pick Spun Pole Design in the Calculation Gallery and add it to your project with "Start Calculation". The input panel is on the left, with Select from Catalog at its top. On the right are five tabs: 3D View, Design, Detailed Design, Takeoff and Test Simulation. Analyze and Design sits on the 3D View tab.

SectionData you define
GeometryPole length, foundation depth, base and top diameters, concrete cover
MaterialConcrete class, steel grade and the material safety factors
LoadsA tip load and torsion, or point loads, cross-arms and equipment at any height
Design OptionsThe TEDAŞ product class and the bar and spiral diameters the design may use
The Spun Pole Design screen. On the left the input panel with Select from Catalog at the top and the Geometry section open: pole length 9.3 m, foundation depth 1.2 m, base section 315 / 186 mm, top section 175 / 93 mm, cover 15 mm and the wall thicknesses at both ends; below it the closed Material, Loads and Design Options sections and the status Analyzed with the engine version. On the right the 3D View tab with the tapered pole standing in its foundation, a double cross-arm near the top and the tip load drawn as an arrow.
The Spun Pole Design screen. On the left the input panel with Select from Catalog at the top and the Geometry section open: pole length 9.3 m, foundation depth 1.2 m, base section 315 / 186 mm, top section 175 / 93 mm, cover 15 mm and the wall thicknesses at both ends; below it the closed Material, Loads and Design Options sections and the status Analyzed with the engine version. On the right the 3D View tab with the tapered pole standing in its foundation, a double cross-arm near the top and the tip load drawn as an arrow.

Selecting from the catalogue

Select from Catalog opens the KamBeton SBA catalogue. The list starts with one representative pole for each top diameter; "Show all types" lists every length and nominal load. Picking a pole fills the length, the outer and inner diameters at the base and the top, the foundation depth and the tip load. The catalogue rates the nominal tip load in kilograms, and it is entered as kilonewtons: 400 kg becomes 4 kN. Nothing is calculated until you run Analyze and Design.

The manufacturer publishes the outer diameters and the weight of each pole. The catalogue's inner diameters are derived from those two, so check the wall thickness against the drawing of the pole you order.

Geometry

You enter the pole length and the foundation depth. The buried length is taken as fixed in the soil, so the analysis starts at ground level and no station lies in the buried part. The note under the foundation depth repeats the ground level.

The base and top sections each take an outer and an inner diameter, and the diameters vary linearly between them. The wall thickness at both ends is shown under the cover.

The concrete cover is measured to the outside of the spiral, so the cover to a longitudinal bar is this value plus the spiral diameter. The form starts at 15 mm, the value TS EN 12843 Annex B gives for a hollow section in exposure class XC4 with concrete below C40/50. Change it if your conditions are different.

Material

You select the concrete class and the steel grade. The material safety factors γc\gamma_c and γs\gamma_s start at 1.5 and 1.15, and the design strengths fcdf_{cd} and fydf_{yd} they give are shown below them. These factors apply to the TS 500 design check. The TEDAŞ safety factor and the bending test simulation work with characteristic strengths, without them.

Loads

The Loads section has two modes.

Simple is for the usual case, where the specification gives the pole a single tip load. You enter the horizontal Tip Load, its Angle in plan, a Tip Torsion if there is one, and the Tip Offset, the distance down from the top at which the load acts. The form starts the offset at 0.25 m, where TEDAŞ-MLZ/99-34 clause 2.6 applies the tip force.

Detailed lets you place loads at any height:

LoadWhat you enterHow it acts on the pole
Point loadHeight, horizontal force, angleShear and bending below its height. The tip load is the first point load
Tip torsionA torsional momentConstant torsion below the tip load. Cross-arm torsion is added to it separately
Cross-armDouble or single arm, height, arm length, self weight, vertical and horizontal load, angleA double arm is symmetric: its vertical loads add axial force only. A single arm also bends the pole with its self weight at mid-arm and its vertical load at the tip. In both, the horizontal load is the net imbalance, and it produces torsion equal to the load times the arm length
EquipmentTransformer, projector or box platform, height, angle, dimensions and weightsThe transformer platform sits off-centre, so the deck and the transformer bend the pole. The pole passes through the centroid of the projector platform, and a box sits on the axis, so these two add axial force only

Wind and ice loads are not generated. The tip load in a utility's specification usually already includes them; any additional share can be entered as a point load or as a cross-arm's horizontal load.

The Loads section in Detailed mode: the tip load as the first point load, at 9.05 m with 4 kN and an angle of 0°, Add Point Load, the tip torsion at 0, and the card of Cross-arm 1 as a double arm at 8.8 m with a 0.5 m arm, 0.5 kN self weight and 1 kN vertical load. On the right the 3D view in Analytical mode with Loads selected, the buttons for the other views beside it, and the pole with the tip load and the cross-arm reduced to its axis and labelled at their heights.
The Loads section in Detailed mode: the tip load as the first point load, at 9.05 m with 4 kN and an angle of 0°, Add Point Load, the tip torsion at 0, and the card of Cross-arm 1 as a double arm at 8.8 m with a 0.5 m arm, 0.5 kN self weight and 1 kN vertical load. On the right the 3D view in Analytical mode with Loads selected, the buttons for the other views beside it, and the pole with the tip load and the cross-arm reduced to its axis and labelled at their heights.

Design options

Product class (TEDAŞ) selects the safety factor the pole is designed to.

ChoiceTarget safety factor
Urban LV/MV shared network2.00
Long-span overhead line2.21
My own safety factorThe value you enter
No class — TS500 onlyNone: the ratio is reported for information

A selected class turns the safety factor into a design requirement alongside TS 500: the longitudinal steel is raised until the target is reached. New calculations start with the urban class.

Longitudinal Rebar Candidates and Spiral Rebar Candidates are the diameters the design may use. At each station it takes the smallest diameter in the list that is adequate, so the result tends towards many thin bars. If you want thicker bars, take the thin diameters out of the list.

Analyze and Design

Analyze and Design on the 3D View tab runs the first stage. Three things happen:

  1. The internal forces and the required longitudinal steel and spiral are computed at every station.
  2. If you have no zones yet, one rebar zone and one stirrup zone covering the whole pole are proposed, sized for the most demanding station.
  3. Those zones are checked at once, and the 3D view switches to its analytical mode.

In Analytical mode the buttons along the top choose what is drawn on the pole: Loads, Required As, Required Stirrup, or one of the six internal force diagrams N, V2, V3, M22, M33 and T. Physical returns to the pole itself.

The 3D View tab in Analytical mode with Required As selected: along the pole the required longitudinal steel area, largest at ground level and decreasing towards the top.
The 3D View tab in Analytical mode with Required As selected: along the pole the required longitudinal steel area, largest at ground level and decreasing towards the top.

Reading the Design tab

The bar at the top of the Design tab gives the verdict: Design Adequate, Design Inadequate or Not verified — Check when the zones have changed since the last check. Beside it are the number of rebar and stirrup zones, the approximate steel weight and how it compares with a single zone. The buttons below it are How to use?, Generate Report and Check.

The TEDAŞ Safety Factor card below gives the factor against its target with a PASS or FAIL badge, the nominal and breaking tip forces, the first section to reach capacity, the lever arm and the characteristic strengths used. With a product class selected the verdict covers both requirements: a pole whose sections all pass but whose factor stays below the target is reported as Design Inadequate, and the bar says by how much.

The two drawings show the zones against what the stations require: Longitudinal Rebar Zones and Design Envelope and Stirrup Zones and Design Envelope. Beside them are the sections at the upper and lower ends of the zone, with the bars, the spiral and the clear spacing between bars. Under the drawings each zone has its card: start and end height, count and diameter for a rebar zone; type (spiral or hoop), diameter, spacing and single or double wrap for a stirrup zone. The badge on each card says whether the zone is adequate, not covered, does not fit geometrically, or is inadequate.

To split a zone, Shift-click its band in the drawing at the height you want, or use Add Rebar Zone, which halves the longest zone. After any change, Check verifies the new layout.

The Design tab. At the top the bar with Design Adequate, 5 Rebar Zones and 1 Stirrup Zone, approximate steel 77 kg and 25% more economical than a single zone, and the buttons How to use?, Generate Report and Check. Below it the TEDAŞ Safety Factor card: safety factor 2.02 against a target of 2.00 with PASS, nominal tip force 4.00 kN, breaking tip force 8.09 kN, first section to reach capacity at z = 5.20 m and the characteristic strengths. Below that the longitudinal rebar zones from 28Ø8 at the base to 5Ø8 at the top against the required envelope, the single spiral zone Ø3/96 against its envelope, and the upper and lower sections of the selected zone.
The Design tab. At the top the bar with Design Adequate, 5 Rebar Zones and 1 Stirrup Zone, approximate steel 77 kg and 25% more economical than a single zone, and the buttons How to use?, Generate Report and Check. Below it the TEDAŞ Safety Factor card: safety factor 2.02 against a target of 2.00 with PASS, nominal tip force 4.00 kN, breaking tip force 8.09 kN, first section to reach capacity at z = 5.20 m and the characteristic strengths. Below that the longitudinal rebar zones from 28Ø8 at the base to 5Ø8 at the top against the required envelope, the single spiral zone Ø3/96 against its envelope, and the upper and lower sections of the selected zone.

When a code detailing rule fails while the sections still carry the load, the bar shows a separate notice outside capacity badge. These notices do not change the verdict; Details lists them with the station heights they apply to.

Analysis and Design Station Points, closed at the bottom of the tab, is the table behind the envelopes. The stations are spaced at regular intervals along the pole, with one more at every height a load acts on. Each row gives the height, the outer and inner diameter, the six internal forces, the moment capacity, and the longitudinal bars and spiral that station alone would need. The values are a guide for laying out the zones; the verdict comes from the check of the zones themselves.

The Analysis and Design Station Points table, opened. One row per station from the tip down to the ground, with z, the outer and inner diameter, N, V2, V3, M22, M33, T, the moment capacity, the longitudinal rebar with its As and the stirrup or spiral with its Asw/s.
The Analysis and Design Station Points table, opened. One row per station from the tip down to the ground, with z, the outer and inner diameter, N, V2, V3, M22, M33, T, the moment capacity, the longitudinal rebar with its As and the stirrup or spiral with its Asw/s.

Optimising the zones

Laying out the rebar zones by hand is not necessary. Optimise Zones computes the lightest layout for every number of zones and shows them together. In the window you choose the bar diameter, the largest number of zones, the shortest zone you accept and the stock bar length the shop cuts from. The chart plots the longitudinal steel against the number of zones for each candidate diameter, and the table lists, for each zone count, the takeoff, the steel actually purchased once the offcuts are counted, the waste and the layout.

The row marked most economical buys the least steel; among rows that buy the same, it is the one with the fewest zones. Select it picks that row, and Apply replaces the rebar zones with it and runs the check again. The weights cover longitudinal steel only; the exact takeoff comes from the Takeoff tab. How the search works is described on the Spun Concrete Pole Design page.

Optimising the rebar zones

Detailed Design

The Detailed Design tab opens on the two Most Critical Sections: the section that governs the longitudinal steel and the section that governs the transverse steel, usually at different heights. Inspect by Zone has a button for each rebar zone and each stirrup zone, and opens the governing station of that zone; its calculation is fetched when you click it.

The selected section has three tabs. Detailed Calculation lists the steps in groups (longitudinal reinforcement, flexure, shear in each direction, torsion and detailing rules), each with the formula, the numbers substituted into it and the outcome, and the code clause where the step comes from one. Interaction Diagram shows the section's N-M envelope with its demand, and Section State the fiber stresses, which are computed on demand with "Compute fiber state".

The Detailed Design tab. At the top the sections governing longitudinal rebar at z = 5.20 m and transverse rebar at z = 9.05 m, and the zone buttons #1 to #5 for the rebar zones and #1 for the stirrup zone. Below them the longitudinal layer at z = 5.20 m with the Detailed Calculation tab open and its Flexure group expanded.
The Detailed Design tab. At the top the sections governing longitudinal rebar at z = 5.20 m and transverse rebar at z = 9.05 m, and the zone buttons #1 to #5 for the rebar zones and #1 for the stirrup zone. Below them the longitudinal layer at z = 5.20 m with the Detailed Calculation tab open and its Flexure group expanded.

Takeoff and the detail drawing

The Takeoff tab produces the exact quantities from the zones you applied. The detailing options follow shop and specification practice:

OptionStarts atWhat it sets
Fixed lap (ר)BlankBlank uses the lap length the TS 500 formula gives
Max bar length (mm)12000The stock length bars are cut from
Waste (%)0Added to every weight
Spiral end extra turns1.5Extra turns at each end of a spiral
Max splice at one section (%)50Above half, the lap lengths are multiplied by 1.5 as TS 500 requires

Generate Final Takeoff + Drawing gives the total steel with its longitudinal and spiral parts, the concrete volume with the steel per cubic metre, a summary by diameter and the bar schedule. Each mark in the schedule has its diameter, count, unit and total length, the height range it covers and a note such as the end anchorage length. The development and lap lengths used are listed below the schedule.

The Takeoff tab after Generate Final Takeoff + Drawing: the detailing options with their starting values, the cards Total Steel 79.1 kg, Longitudinal 75.4 kg, Transverse (spiral) 3.7 kg and Concrete 0.303 m³, the takeoff summary by diameter, and the bar schedule with five Ø8 marks of different lengths and the spiral.
The Takeoff tab after Generate Final Takeoff + Drawing: the detailing options with their starting values, the cards Total Steel 79.1 kg, Longitudinal 75.4 kg, Transverse (spiral) 3.7 kg and Concrete 0.303 m³, the takeoff summary by diameter, and the bar schedule with five Ø8 marks of different lengths and the spiral.

Below the schedule is the detail drawing, and Download DXF saves it. The preview shows the drawing as it is laid out in model space, where the sections are drawn at full size and therefore look small beside the pole. The DXF also carries an A4 fabrication sheet in paper space: the pole elevation, the stirrup and spiral zones, the developed layout of the longitudinal bars, the rebar schedule, the concrete quantity, the base and top sections and the pole's data table, with the sections brought to a readable size by their viewport.

An example A4 fabrication sheet plotted from the DXF's paper space, for a 9.3 m pole with Ø10 bars. On the left the pole elevation in its foundation, the stirrup and spiral zones and the developed layout of the longitudinal bars with their marks and lengths. On the right the rebar schedule with the bar mark table, the concrete quantity, the base and top sections, and the table with the pole type, the top and base diameters and the concrete and steel grades.
An example A4 fabrication sheet plotted from the DXF's paper space, for a 9.3 m pole with Ø10 bars. On the left the pole elevation in its foundation, the stirrup and spiral zones and the developed layout of the longitudinal bars with their marks and lengths. On the right the rebar schedule with the bar mark table, the concrete quantity, the base and top sections, and the table with the pole type, the top and base diameters and the concrete and steel grades.

Test Simulation

The Test Simulation tab predicts what the TS EN 12843 clause 5.5.2 bending test will measure on the reinforcement you applied. Under Test Settings you can enter the concrete and steel strengths you expect from production control; left blank, the catalogue classes are used. These values are used by the simulation only; the design always uses the ordered classes. The Elastic limit / safety factor ratio starts at 0.75: the specification's annex figure marks the elastic limit at 1.65 P for the 2.21 class, and 1.65 / 2.21 is 0.75. Simulate Test runs the analysis, and its result is saved with the calculation.

The Pushover Curve plots the tip force against the lateral displacement. Dashed lines mark the computed events, and solid lines the specification's limits for the elastic limit and for breaking. The table below gives each event (the nominal tip force, cracking onset, first yield and breaking) with its force, its ratio to the nominal force, the lateral displacement, the section where it occurs, the specification limit and the difference from it.

The Test Simulation tab. On the left the Test Settings with the expected strengths left at the catalogue class, the elastic limit / safety factor ratio 0.75 and Simulate Test, and the Method and Scope notes. On the right the pushover curve of tip force in kilograms against lateral displacement in millimetres, with cracking at 64 kg, the nominal load at 408 kg, yield at 633 kg (1.55×P) above the elastic limit of 1.50×P, and failure at 848 kg (2.08×P) above the breaking limit of 2.00×P. Below them the table of predicted events with the safety factor from the pushover, 2.08×P.
The Test Simulation tab. On the left the Test Settings with the expected strengths left at the catalogue class, the elastic limit / safety factor ratio 0.75 and Simulate Test, and the Method and Scope notes. On the right the pushover curve of tip force in kilograms against lateral displacement in millimetres, with cracking at 64 kg, the nominal load at 408 kg, yield at 633 kg (1.55×P) above the elastic limit of 1.50×P, and failure at 848 kg (2.08×P) above the breaking limit of 2.00×P. Below them the table of predicted events with the safety factor from the pushover, 2.08×P.

This tab gives no verdict: whether the design is adequate is decided on the Design tab. The breaking force here can differ slightly from the TEDAŞ card's, because the pushover uses a concrete model that carries tension while the design uses the code's stress distribution. Test Observations lets you enter the displacements from a real test report next to the prediction; adding or removing a row does not change the computed events.

Generating the report

Generate Report on the Design tab produces the PDF.

SectionContents
1. SummaryThe verdict, the highest demand/capacity ratio of each layer with its height, and the TEDAŞ safety factor
2. GeometryLength, diameters, foundation depth and cover
3. Material and Design ParametersMaterial classes and factors
4. LoadsThe loads you entered and their reduction to the pole axis
5. Internal Force DiagramsN, V2, V3, M22, M33 and T along the pole
6. Longitudinal ReinforcementThe rebar zones against the required envelope
7. Transverse ReinforcementThe stirrup zones against the required envelope
8. Capacity Check SummaryThe check of every zone

These are followed by the governing section of each layer with its detailed calculation steps and the analysis station table. When the bending test has been simulated, its pushover is added; when the takeoff has been generated on the Takeoff tab, the takeoff and the detail drawing are added at the end.

A page of the report: section 6, Longitudinal Reinforcement (Rebar Zones). A table of the five zones with their bars and steel area, and below it the figure of the pole with the zones from 28Ø8 at the base to 5Ø8 at the top beside the required and provided envelope.
A page of the report: section 6, Longitudinal Reinforcement (Rebar Zones). A table of the five zones with their bars and steel area, and below it the figure of the pole with the zones from 28Ø8 at the base to 5Ø8 at the top beside the required and provided envelope.
A page of the report: Pushover Analysis and Bending Test Prediction (TS EN 12843 Clause 5.5.2). The material basis, the table of events with their forces, ratios, displacements and sections, the pushover curve with the specification limits, and the method and scope notes.
A page of the report: Pushover Analysis and Bending Test Prediction (TS EN 12843 Clause 5.5.2). The material basis, the table of events with their forces, ratios, displacements and sections, the pushover curve with the specification limits, and the method and scope notes.

The report follows the language of the interface: run a calculation in the English UI and the report comes out in English.

Publishing and verification

Publish at the top of the page opens the Publishing & Verification window. Publish This Version freezes the calculation as it stands, its inputs and results together, into a copy that does not change, and gives that copy a verification link. Anyone with the link sees the copy read-only, without signing in. Editing the calculation afterwards leaves the copy as it was. Publishing a state that is already published returns the same publication instead of a second one.

While the calculation is in its published state, the window marks it Current. Download PDF with QR, and Generate Report too, then produce the report with a QR code that opens the link. Once an input changes, the report no longer matches the publication and the QR is left out. Publish again to get a link for the new state.

The Publishing & Verification window. Below the explanation of what publishing does, the badge Current, the buttons Publish This Version and Download PDF with QR, and the note that the PDF will include the verification QR code. Under Publications the entry marked Current, with its date, its view count, its verification link and the buttons to copy, open and revoke it.
The Publishing & Verification window. Below the explanation of what publishing does, the badge Current, the buttons Publish This Version and Download PDF with QR, and the note that the PDF will include the verification QR code. Under Publications the entry marked Current, with its date, its view count, its verification link and the buttons to copy, open and revoke it.

The Publications list holds every version with its date and the number of times its link has been opened. Each can be copied, opened or revoked. Revoking is permanent: the link stops working.

Whether the results are current

The state of your result is shown under the input panel.

StateWhat it means
AnalyzedThe saved result is current. The engine version and the time of the run are shown with it
Inputs changedYou changed a design input after the analysis, so the results no longer belong to the pole on screen
Outdated engineThe result was produced with an earlier version of the calculation engine

While the results are out of date, the Design and Detailed Design tabs say so and offer Analyze and Design. The test settings and observations are not design inputs, so changing them leaves the design current.

When you want to study the section's behaviour

This macro designs the pole and checks it against TS 500 and the TEDAŞ safety factor. To study one of its sections on its own, its moment-curvature curve or the effect of prestressing strands, you can model it in the Section Analysis macro. Its step-by-step use is on the How to Use Section Analysis page.

Which rules the calculation applies, how the zones and the safety factor are computed and what it leaves out are covered on the Spun Concrete Pole Design page.