Differential axial shortening in tall buildings and construction stage analysis

Columns and walls shorten by different amounts under vertical load, and the difference accumulates storey by storey. This post covers the causes of the difference, its effect on beams and slabs, why a single-step analysis misleads, and the construction stage analysis that TBDY 2018 requires for tall buildings.

Mustafa Tümer Tan · Founder

Share
Floor slabs of a tall building under construction with a tower crane beside it
On this page

A standard structural analysis loads the building in a single step. The building is calculated as if it had been built weightless and the whole vertical load had then been applied at once. In reality a building rises storey by storey, and each floor is built to its own level after the floors below have started to shorten. In tall buildings the difference in shortening between columns and walls can grow large enough to affect the design of beams and slabs, so it should be calculated together with the construction sequence.

Why don't columns shorten equally?

The shortening of a reinforced concrete vertical member has three components:

  • Elastic shortening. It occurs as soon as the load is applied and depends on the member stress and the elastic modulus of the concrete.
  • Creep. It grows over time under sustained load. Under Eurocode 2 (3.1.4 and Annex B), the creep coefficient depends on the stress level, the age of the concrete at loading, the relative humidity, the concrete strength and the notional size of the member. The notional size is defined as h0=2Ac/uh_0 = 2A_c/u, where AcA_c is the concrete cross-section area and uu is the perimeter of the section exposed to drying.
  • Shrinkage. It is independent of load and comes from the drying of the concrete. Drying shrinkage also depends on the relative humidity and the notional size.

A wall and a column standing side by side may serve the same floors, but their stress levels, reinforcement ratios and notional sizes usually differ. The two members therefore shorten by different amounts under the same load history. The small difference that forms on each storey accumulates on the storeys above.

Effects of the difference in shortening

The difference in shortening creates a level difference between the two supports of a beam. This level difference has the following effects:

  1. Slab tilt. The floor slab departs from the horizontal plane.
  2. Additional forces in beams and slabs. In a beam fixed at both ends, a level difference Δ\Delta between the supports causes an additional moment of 6EIΔ/L26EI\Delta/L^2 at each end, where EE is the elastic modulus, II the second moment of area of the section and LL the beam span. Because the additional moment decreases with the square of the span, the largest effect is seen in short, stiff beams, such as short link beams between a core and a column.
  3. Load redistribution. Because the beams restrain the difference in shortening, part of the load is transferred from the member that shortens more to the member that shortens less.

These effects can also show up as cracking and fitting problems in partitions, the facade and level-sensitive services.

Why does a single-step analysis mislead?

In a single-step analysis the building is modelled as complete and the whole vertical load is applied at once. A shortening column on the ground floor then pulls down the node on the top floor as well. The vertical displacement of a floor is calculated as the sum of the shortening of all floors below it under the full load.

The actual construction process is different:

  1. A floor is built and finished to its level.
  2. As new floors are added on top, the columns and walls below shorten.
  3. Each new floor is built to its own level on top of the floors below as they have shortened so far.

In this process, the beams of a floor only experience the difference in shortening that occurs after that floor is built. A single-step analysis does not account for this sequence, so it calculates a difference in shortening and beam forces that differ from those that will actually occur.

Construction stage analysis

In a construction stage analysis the structure is added to the model storey by storey or in groups of storeys:

  • At each stage only the members built so far and the loads acting so far are taken into account.
  • Newly added members are placed at their own levels, not at the deformed position of the floors below.
  • Creep and shrinkage are calculated at each stage from the age and load history of the concrete. A stage analysis that includes only elastic shortening does not give the time-dependent shortening.

TBDY 2018 makes this analysis mandatory for tall buildings. Under Chapter 13, a tall building is one taller than 70 m for Earthquake Design Classes 1, 1a, 2 and 2a, 91 m for classes 3 and 3a, and 105 m for classes 4 and 4a (13.1.2). For these buildings, a vertical load analysis that considers the construction stages and a wind analysis are carried out before the Stage I earthquake analysis. For reinforced concrete buildings a creep analysis is added (13.4.3.1). The results of the vertical load analysis that considers the construction stages are also used in Stage II (13.5.3.1).

The calculated difference in shortening can be compensated during construction. Column and wall formwork can be set higher by the expected shortening. Floor levels can be re-set on every storey. Steel columns can be fabricated longer by the expected shortening.

Conclusion

In a tall building the shortening of the vertical members depends on the load history of the structure. The difference in shortening should therefore be found not with a single-step analysis but with a calculation that includes the construction sequence and the time-dependent behaviour of the concrete. The results of that calculation feed into the beam design, the level compensation applied during construction and the facade and services details.

Mustafa Tümer Tan

About the author

Mustafa Tümer Tan

Civil engineer (M.Sc.) and founder of StructuralMind.

Get new posts by email

Engineering writing and product notes, straight to your inbox.

Unsubscribe at any time.Privacy Policy

Share

Start calculating in minutes.

Sign up, pick a calculation, and produce your first auditable report.